What Is Ground Investigation? Methods, Process & Reports
A ground investigation is a planned programme of fieldwork, sampling and testing to establish the soil, rock and groundwater conditions beneath a site. At GeoCon, we select locations and methods to answer project specific geotechnical or environmental questions which inform design.
A ground investigation is more than drilling a few holes. We plan the locations and methods to provide useful information about the ground and to address the project’s specific design or risk questions.
Why is ground investigation important?
Ground conditions influence how a development can be designed and built. If the properties of the ground are poorly understood, a project team may have to make design decisions with incomplete information.
A ground investigation can provide information to support:
- Foundation and substructure design.
- Piling, retaining wall and pavement design.
- Assessment of soil strength and settlement.
- Slope stability and earthworks design.
- Groundwater assessment and monitoring.
- Investigation of shallow rock, made ground or buried features.
- Assessment of mining or other known ground risks.
The investigation helps the design team understand the ground at the locations examined. It cannot establish every condition across a site with absolute certainty, so the report should describe the investigation coverage and any limitations.
What happens during a ground investigation?
We design the programme for the project. It may include a review of available information, intrusive fieldwork, testing, monitoring and reporting.
1. Set the investigation objectives
The project team identifies what information it needs. This might include the depth and type of soil, whether rock is present, groundwater conditions, soil strength or the presence of a particular ground risk.
The objectives should relate to the proposed development. For example, an investigation intended to inform foundation design may need different information from one focused on groundwater or potential contamination.
2. Select methods and locations
We consider the anticipated ground, site access, existing structures and the depths or samples required. The techniques and locations need to suit the questions being asked.
Where a site investigation or preliminary assessment has already identified potential risks, those findings may help define the ground investigation programme. Where risks relate to potentially contaminated land, government guidance describes using a proportionate, phased approach to risk assessment and further investigation.
3. Carry out fieldwork and testing
Fieldwork may include trial pits, window sampling, cable percussion boreholes or rotary drilling. Soil and rock may be logged and sampled. In-situ tests, laboratory analysis or monitoring can be included where they are relevant to the project objectives.
4. Report and interpret the results
A factual report sets out the work completed and the data collected. An interpretative report explains what the findings mean for the project and may provide engineering parameters or recommendations, depending on the agreed scope.
It is important to confirm what the client needs before the work begins. A report containing factual records alone may not answer design questions that require interpretation.
Common ground investigation methods
Different methods provide different types of information. At GeoCon, our ground investigation work can include trial pits, window sampling, cable percussion and rotary boreholes, together with groundwater and ground gas monitoring where the project requires it.
Trial pits
Trial pits expose shallow ground for inspection and sampling. They can help establish near-surface soil conditions and may be used to examine existing foundations where the site and work method allow.
Dynamic Sampling / Window Sampling and Windowless Sampling
These methods collect soil samples through a borehole. They can be useful for investigating shallow ground and are often considered where access or site conditions affect the equipment that can be used.
Cable percussion boreholes
Cable percussion boring can investigate deeper ground through suitable superficial deposits. It also facilitates sampling, in-situ testing and the installation of groundwater and / or gas monitoring points where required.
Where access or headroom is restricted, we also use cut-down cable percussion rigs for suitable locations, including inside existing buildings and basements.
Rotary drilling and coring
Rotary drilling can be used to investigate rock or other ground that requires rotary techniques. Open-hole rotary drilling can help investigate rockhead and potential mine workings; rotary coring collects core samples when more detailed information about the rock is needed.
Where a former mine shaft may be present, we can use a technique called spiral drilling to investigate changes in depth to rockhead that may identify the location of a mine shaft. This is a specialist technique and is different from standard drilling and dynamic probing.
Dynamic probing
Dynamic probing records the resistance encountered as a probe is driven into the ground. Where suitable, it can add information about near-surface ground strength alongside other investigation methods.
Testing and monitoring
The investigation may include in-situ testing, laboratory analysis or monitoring of groundwater and ground gases. These activities are selected to address specific requirements; they are not automatically necessary on every site.
The method choice should be based on the intended use of the results. A technically detailed investigation is only useful if it answers the design or risk questions that prompted the work.
Our experience: ground investigation at a listed theatre
For a proposed extension to the listed Theatre Building in Mold, we investigated the ground and existing foundations to inform the project.
The work included two cable percussion boreholes, five machine-excavated trial pits, four hand-dug pits to expose the existing foundations, two CBR tests and the installation of two combined gas and groundwater monitoring standpipes. Monitoring continued over six months, alongside geotechnical and chemical laboratory analysis.
We recorded natural strata to 13 metres below ground level and exposed and recorded the existing foundations. We completed the fieldwork on schedule and resurfaced the areas beneath the tarmac afterwards.
Read the Theatre Building Mold case study.
Ground investigation and site investigation: what is the difference?
The terms are often used interchangeably, but they can describe different scopes. Site investigation may refer to the wider assessment of a development site, including desk-based research, a walkover and consideration of environmental risks. Ground investigation often refers to fieldwork and testing that characterise the soil, rock and groundwater, particularly for engineering design.
There is no universal boundary between the two terms. We often use ground investigation to describe the fieldwork part of a broader site investigation, and we also provide ground investigation as a standalone service for design teams. The work required should therefore be specified in the project brief.
When might a ground investigation be needed?
A ground investigation may be appropriate before a development is designed or built when the project needs information about the ground. It can also be used where existing information is incomplete or identifies risks that need to be examined in more detail.
The required scope depends on the project, the site and any planning requirements. Where land contamination or stability issues are relevant, the National Planning Policy Framework says adequate site assessment information, prepared by a competent person, should be available. A planning authority may request information about ground or contamination risks, but the appropriate investigation depends on the circumstances of the site and proposal.
Our expertise and approach to reporting
Technical expertise: choosing methods for each site
We provide ground investigation fieldwork and geotechnical consultancy for development and engineering projects. Our methods include trial pitting, window and windowless sampling, cable percussion and rotary drilling. We can also undertake testing and monitoring when they are relevant to the project. We select a suitable combination for the ground, access, structures and information required; no single method answers every question.
Clear reporting and a transparent scope
Before work begins, the investigation objectives and reporting requirements should be clear. Our factual reporting records the work and results. Where interpretation is included in the agreed scope, we explain what the findings mean for the project and identify any recommendations or further investigation needed. Results describe the ground at the locations examined, so we also make the coverage and relevant limitations clear.
Founded in 2007, we are an independent site investigation consultancy and contractor based in Marple, Stockport, working across the UK. To discuss the fieldwork and reporting needed for a project, see our ground investigation service. If the project also needs a broader environmental assessment, see our site investigation service.
Frequently asked questions
Does a ground investigation always involve boreholes?
No. Boreholes are one option. Depending on the objectives, ground conditions and access, a programme may use trial pits, window sampling, rotary methods or a combination of techniques.
What information does a ground investigation provide?
It can provide information about the ground encountered at the investigation locations, including soil and rock profiles, samples, test results and groundwater observations. The scope determines whether the report also interprets these findings for design.
Is ground investigation the same as geotechnical investigation?
The terms overlap. A geotechnical investigation focuses on the ground information needed to understand engineering behaviour and support design. A ground investigation may include this work, alongside other sampling or monitoring required by the project.
Is a ground investigation always required for planning permission?
No single investigation is required for every project. Planning requirements depend on the proposal and site. Where ground or contamination concerns exist, the local authority may request proportionate information to help assess them.
How much does a ground investigation cost?
Cost depends on the site, access, investigation depth and methods, the number and location of exploratory points, testing and reporting requirements. We can discuss a suitable scope for a specific project.
Need information about ground conditions for a project? Talk to GeoCon about ground investigation or call 0161 713 0174.